Pertamina targets refinery upgrade by end-2024
Indonesian NOC on track to complete Balikpapan expansion on schedule
Work to increase the capacity of Indonesia’s Balikpapan refinery from 260,000bl/d to 360,000bl/d are now more than 40pc complete, says NOC Pertamina The development will also raise the refinery’s Nelson Complexity Index rating to 8.8 from 4.4, meaning it will be able to produce more complex products, including those that meet Euro 5 quality standards. The expansion project “is one of the pillars of [Indonesian] energy independence”, says Pertamina. The upgraded refinery will have a greater “flexibility in processing economical crude oil available in the market”, the NOC adds. Pertamina has also committed to a relatively modest goal of 17pc “new and renewable” generation capacity by 2030, up
Also in this section
23 April 2024
Cheaper Russian barrels and lower overall crude prices have helped cut key oil consumer’s import bills in election year
22 April 2024
Pursuing three different goals as part of the same package may mean achieving none of them
22 April 2024
Beijing’s renewed targeting of NOC management could threaten investment
19 April 2024
Cairo’s currency problems have hindered investment, but Pharos sees considerable potential as Egypt emerges from crisis