Countdown to Mozambique LNG restart
Mozambique’s insurgency continues, but the security situation near the LNG site has significantly improved, with TotalEnergies aiming to lift its force majeure within months
TotalEnergies is aiming to lift its four-year-old force majeure on the $20b Mozambique LNG project in the coming months amid improved security conditions. However, the French major is first seeking a freeze on engineering, procurement and construction (EPC) costs. Given the prolonged delay, the project’s overall cost could increase by up to 15% above the original estimate at the time of FID in June 2019. Operations at Mozambique LNG were suspended in April 2021 when TotalEnergies declared force majeure and withdrew all personnel from the site in Afungi, located in Cabo Delgado province, northeastern Mozambique. The decision followed an incursion by Islamist insurgents into the nearby town of
Also in this section
21 April 2026
After overcoming a COVID-induced demand collapse with several years of successful market management, geopolitical events have conspired to provide the pact’s biggest test to date
21 April 2026
The regime’s policy of using nuclear ambiguity as a deterrent may have failed but it has realised it has other cards to play, while its neighbours are reappraising their approach to security
21 April 2026
As the global energy system undergoes a fundamental realignment, Algihaz Holdings has established itself as a critical player bridging conventional energy markets and the next generation of renewable infrastructure.
21 April 2026
The 25th WPC Energy Congress is taking place from 11-15 October 2026 at the Riyadh Front Exhibition & Conference Center.






