LNG delays push Pakistan towards coal
Pakistan’s hope that the growth of LNG imports would relieve energy-induced constraints on economic growth has been dashed by project delays. Instead, it has turned to the IMF for economic help and coal to relieve energy shortages
When Pakistan began importing LNG in March 2015, marking its first imports of natural gas in any form, some hoped that the country would become a 30mn t/yr market as early as 2020. The optimists—notably former prime minister Shahid Khaqan Abbasi—thought imports would help the nation escape energy shortages so severe and prolonged that they had constrained economic growth for more than a decade. Five years and a change in government later, expectations are tempered by the slow pace of LNG import infrastructure development. The Engro Elengy Terminal that started up in March 2015 was followed in November 2017 by the Pakistan GasPort (PGP) project. Since then, nothing. LNG imports had been gro
Also in this section
15 November 2024
With Chevron and AIM-listed Challenger Energy having completed their Uruguayan farm-out deal, Challenger CEO Eytan Uliel updates Petroleum Economist on the firm's progress in the frontier basin
14 November 2024
The country is seeking to secure its position as a major global refiner and meet rising domestic requirements
13 November 2024
IOCs are focused on the next wave of exploration activity in Namibia and are keen to learn from one another’s results