BP exits $55b Australian green mega-project
Oil major cites strategy reset as it walks away from Australian Renewable Energy Hub, leaving partner InterContinental Energy to lead one of world’s largest green hydrogen projects
BP has withdrawn from the $55b Australian Renewable Energy Hub (AREH) mega-project in the Pilbara region, in a blow to Western Australia’s green hydrogen ambitions. The oil major is the operator and biggest shareholder in AREH, one of the world’s largest projects, with a 63.57% take, alongside developer InterContinental Energy with a 26.39% holding and Serbia-based CWP Global with a 10% interest. BP said its exit from the project—which envisages green hydrogen production of 1.6mt/yr with 26GW of renewable power capacity – reflects it recent change in strategy. The company, which is under pressure to boost profitability by selling assets and to prop up its sliding share price, announced in Fe
Also in this section
9 March 2026
Hydrogen has not stalled in the UK because the technology does not work. The problem is that the system around it does not yet move at the speed required
4 March 2026
Turmoil in Middle East reminds nascent clean hydrogen sector that its future prospects are dependent on global energy markets and geopolitics
25 February 2026
Low-carbon hydrogen and ammonia development is advancing much more slowly and unevenly than once expected, with high costs and policy uncertainty thinning investment. Meanwhile, surging energy demand is reinforcing the role of natural gas and LNG as the backbone of the global energy system, panellists at LNG2026 said
18 February 2026
Norwegian energy company has dropped a major hydrogen project and paused its CCS expansion plans as demand fails to materialise