Porthos counts costs of construction delays
Netherlands’ flagship CCS project targets 2026 start up after legal challenge derails original construction timetable
The developers of the Netherlands’ flagship Porthos CCS facility are conducting a review of the project’s costs following a two-year delay in construction because of a legal challenge on environmental grounds. The cost of the project, which is a joint venture between Dutch gas company Energie Beheer Nederland, Dutch gas transmission system operator Gasunie and the Port of Rotterdam Authority, has previously been projected at €500m ($544m). But construction has been delayed due to a challenge launched by environmental group Mobilisation for the Environment in November 2021. The Dutch Council of State recently ruled against the environmental group’s claims that nitrogen emitted during the cons

Also in this section
18 February 2025
Demand for CCS to abate new gas-fired plants is rising as datacentres seek low-carbon power, Frederik Majkut, SVP of industrial decarbonisation, tells Carbon Economist
11 February 2025
Rising prices have added to concerns over CBAM impact on the competitiveness of EU manufacturing
7 February 2025
Norwegian energy company slashes spending on low-carbon sectors as transition decelerates
30 January 2025
The UAE’s oil and gas company puts its faith in technologies including CCS and AI to deliver its emission-reduction goals