Porthos counts costs of construction delays
Netherlands’ flagship CCS project targets 2026 start up after legal challenge derails original construction timetable
The developers of the Netherlands’ flagship Porthos CCS facility are conducting a review of the project’s costs following a two-year delay in construction because of a legal challenge on environmental grounds. The cost of the project, which is a joint venture between Dutch gas company Energie Beheer Nederland, Dutch gas transmission system operator Gasunie and the Port of Rotterdam Authority, has previously been projected at €500m ($544m). But construction has been delayed due to a challenge launched by environmental group Mobilisation for the Environment in November 2021. The Dutch Council of State recently ruled against the environmental group’s claims that nitrogen emitted during the cons
Also in this section
14 January 2025
Bioenergy will be a key part of the energy transition as the world decarbonises, and Brazil is set to be a major player in the sector
14 January 2025
The region has ample resources of both gas and renewable energy and developing both will be vital to the global effort to reduce emissions
13 January 2025
The region’s fast-growing economies stand at a pivotal juncture, with the opportunity to drive a sustainable growth strategy that will keep the world’s net-zero ambitions alive
10 January 2025
Global energy demand keeps rising, and digital technology will play a crucial role in both meeting that demand and doing so in a sustainable way